16 — Capacity Planning¶
Capacity planning is the discipline that turns reliability from firefighting into forecasting. SREs that don't forecast end up firefighting capacity. The capacity-planning loop is the upstream feed that prevents
doc 15from being your weekly reading.
This chapter assumes the queueing math from doc 00 §16 (Little's law, M/M/1 saturation) and the SLO machinery from doc 13. Where SLOs tell you if you're failing, capacity planning tells you when you will.
Table of Contents¶
- Thesis
- The capacity loop
- Headroom: the only metric that matters
- Forecasting models
- USE-driven capacity (the per-resource walk)
- Queue theory in production
- Load testing: closed-loop, open-loop, ramp
- Provisioning patterns: vertical, horizontal, autoscaling, cells
- The capacity planning artifact
- Multi-region capacity
- Cost-bounded capacity
- Capacity SLIs and platform SLOs
- The chicken-and-egg of new services
- Worked example: a 12-month checkout forecast
- Pitfalls
- Mental models
1. Thesis¶
Three claims:
- Headroom is a leading indicator; latency and errors are lagging. A capacity-planned org sees the iceberg coming; a capacity-reactive org hits it.
- Capacity planning is forecasting + a buffer. Not "we have N CPUs"; "we have headroom for 6 months at projected growth, with a 50% buffer for surprise."
- The forecast is wrong. All forecasts are wrong. The point is bounded wrong — calibrated to known uncertainty — and revisited often. A monthly capacity review with a forecast you constantly update beats a perfect annual one.
If your team only knows it's out of capacity when latency burns the SLO, you don't have capacity planning. You have capacity fire suppression. This chapter is the upstream practice.
2. The Capacity Loop¶
┌──────────────┐
│ measure │ current usage by resource per service
│ current │ (CPU %, mem RSS, queue depth, p99 latency,
│ usage │ conn pool wait, disk IOPS, etc.)
└──────┬───────┘
│
▼
┌──────────────┐
│ forecast │ project usage forward N months at expected growth
│ growth │ (linear, seasonal, business-driven)
└──────┬───────┘
│
▼
┌──────────────┐
│ determine │ required capacity = forecast × buffer factor (1.5-2×)
│ required │
│ capacity │
└──────┬───────┘
│
▼
┌──────────────┐
│ procure / │ scale-out, larger instances, new region, new cells
│ provision │ (procurement lead time matters!)
└──────┬───────┘
│
▼
┌──────────────┐
│ validate │ load test that capacity actually delivers
│ via load │ (claimed != actual, especially with autoscaling)
│ test │
└──────┬───────┘
│
▼
┌──────────────┐
│ re-measure │ track forecast accuracy; adjust models
└──────┬───────┘
│
└─────────► back to top, monthly cadence
The loop runs forever. Skipping any step means the next iteration is reactive.
3. Headroom: The Only Metric That Matters¶
Headroom = (current capacity − current usage) / current capacity.
If your service runs at 60% CPU, headroom is 40%. If queue depth is 200 of a 1000-slot queue, headroom is 80%.
3.1 Why headroom, not utilization¶
Utilization is the present tense. Headroom is the forward-looking form: how much margin do I have before saturation kills me?
The queueing math (doc 00 §16.4) shows utilization > 80% causes geometric latency growth. So the operational target is ≥ 30% headroom at peak — meaning peak utilization ≤ 70%. Below 30% headroom, you're in the geometric-degradation zone; one bad day breaks SLOs.
3.2 Headroom by resource¶
Headroom is per-resource, not per-service. A service can have 80% CPU headroom and 5% connection-pool headroom — and the latter will kill it. The capacity dashboard shows headroom per (service × resource) cell.
CPU MEM CONN POOL QUEUE IOPS
checkout-svc 45% 62% 15% 80% 70%
auth-svc 80% 60% 35% 90% 80%
order-svc 30% 25% 65% 70% 60% ← red on CPU+MEM
The order-svc here has a capacity emergency. Two resources below 30% headroom; scale-out is needed now, not next quarter.
3.3 The 30/50/70 rule¶
A practical heuristic:
- ≥ 70% headroom: comfortable. New features fine.
- 50–70% headroom: monitor monthly; plan scaling for next quarter.
- 30–50% headroom: scaling action this quarter; alerts to capacity team.
- < 30% headroom: capacity emergency; immediate action; potentially freeze risky deploys.
These thresholds are resource-by-resource, not aggregate. Any one resource below 30% is the emergency.
4. Forecasting Models¶
The science of "how much will we need?"
4.1 Linear¶
Simple. Wrong, but a useful default. Works when: - Traffic grows steadily with linear customer acquisition. - Service fan-out is constant. - No seasonality.
Fails when traffic has spikes, holidays, viral moments. The default is "good enough for 80% of services for next 6 months." Use as the baseline; layer corrections on top.
4.2 Seasonal¶
Decompose into trend + season + residual (statsmodels: STL decomposition; or just visual inspection).
Standard for: - E-commerce (Black Friday, Cyber Monday, holidays) - Media (sports playoffs, election nights, premieres) - Public sector (April tax deadlines)
The hard part is the period. Daily, weekly, monthly, quarterly, annual all have different signals. Tools: Prophet, statsmodels, internal forecasting libraries. Most observability vendors offer some seasonal forecasting in dashboards (Datadog, Honeycomb).
4.3 Business-driven¶
Sometimes the forecast comes from product/sales: "we're acquiring 5,000 enterprise customers next quarter, each at ~10× current per-user load."
Capacity planning takes the business plan as an input, not an output. The question becomes: given this business plan, what capacity do we need? The math is straightforward; the input is what's hard.
4.4 Compound growth¶
Many services grow by feature usage and user count and per-user activity. The compound:
Each factor has its own growth rate. Compounding 3% monthly user growth × 5% monthly feature growth = ~8% monthly compound, ~150% annual. Linear forecasts massively under-estimate.
4.5 The forecast envelope¶
Always express forecasts as ranges, not points:
Plan for the expected case; have a buffer that covers stretch; have a contingency plan for black-swan. A point estimate is a lie.
4.6 The "wait and see" anti-pattern¶
Many teams under-forecast and plan to scale reactively. This works only if: - Provisioning is < 1 day (autoscaling, cloud). - Load tests confirm scaling actually delivers. - The cost of being wrong is small.
For self-managed infra, multi-region, or hardware-bound (GPU, TPU), reactive doesn't work — lead times are weeks to months. Plan ahead.
5. USE-Driven Capacity¶
The per-resource walk. For every resource, ask: utilization, saturation, errors. Headroom is the gap to capacity.
5.1 The per-service capacity matrix¶
service: checkout-svc
─────────────────────────────────────────────────────────────────────
RESOURCE UTILIZATION SATURATION ERRORS HEADROOM FORECAST
CPU (cores) 45% load_avg=2.1 0 55% +30% in 6m
Memory 62% swap_in=0 OOM=0 38% +20%
Connection pool 35/200 used wait_ms=0.5 0 82% +50%
Goroutines 12k sched_lat=µs 0 OK +25%
Queue depth 150/1000 0 0 85% +30%
DB connections 8/20 wait_ms=2 0 60% +50%
Disk IOPS 400/1000 0 0 60% +30%
File descriptors 200/65k 0 0 99% OK
─────────────────────────────────────────────────────────────────────
Read top to bottom. The lowest headroom in the column is the bottleneck. The forecast column projects out — even if today's headroom is 38%, if growth is +50%, you're at 0 headroom in 6 months.
5.2 The bottleneck migrates¶
A common pattern: scale CPU (the obvious bottleneck), and now memory becomes the bottleneck. Scale memory; now connection-pool saturates. Scale pool; now DB connections saturate. Scale DB; now disk IOPS.
The bottleneck always migrates. Capacity planning is the discipline of identifying which one is next, not just the current one. The matrix above shows you all of them at once.
5.3 USE for non-obvious resources¶
Easy resources (CPU, mem, disk) get attention. Sneaky resources (often the actual cause of outages):
- Connection pools. The DB driver might have a 10-conn pool that's totally invisible to ops dashboards.
- Thread pools / goroutine schedulers. Scheduling latency under load.
- Kernel structures. Conntrack table, file descriptors, ephemeral ports, socket buffers.
- Object pools in languages like Java (heap, PermGen) or Go (sync.Pool).
- Cache warm state. A cache "with capacity X" often serves at full utility only when warm; cold, it's effectively saturated.
- Quotas at downstream services. S3 list-bucket QPS, rate limits on third-party APIs.
USE-walking these every quarter catches surprises. node_exporter covers the kernel side; instrumentation in app code covers the rest.
6. Queue Theory in Production¶
The math that explains why utilization > 80% breaks things.
6.1 Little's law (revisited)¶
Practical use: instrument all three. Verify that requests in flight × service time = throughput × latency. When the equation breaks, you have a measurement bug.
6.2 M/M/1 wait time formula¶
The fundamental capacity equation:
| Utilization ρ | Wait time multiplier |
|---|---|
| 0.50 | 1.0× |
| 0.70 | 2.3× |
| 0.80 | 4.0× |
| 0.90 | 9.0× |
| 0.95 | 19× |
| 0.99 | 99× |
A service running at 99% CPU has 99× the queueing latency of one at 50%. This is why "run hotter to save money" backfires — past 80%, latency is no longer linear in cost.
6.3 M/M/c (multi-server)¶
For c parallel servers (e.g., a worker pool of c workers):
More servers = more graceful degradation. A 1-server pool at 90% utilization is broken; a 10-server pool at 90% utilization is just busy. This is why "scale horizontally" is generally better than "scale up" for latency-sensitive services.
6.4 Queueing-aware autoscaling¶
Most autoscalers target CPU (e.g., scale to keep CPU at 70%). For latency-sensitive services, target queueing:
- HPA + custom metric: queue depth or scheduling latency.
- Scale up before CPU saturates to keep wait time low.
This is the right policy for latency SLOs, even though it costs more steady-state.
7. Load Testing¶
The only way to validate that "claimed capacity" matches "actual capacity."
7.1 Types¶
| Type | Pattern | Reveals |
|---|---|---|
| Smoke | Light load, normal traffic | Are we instrumented correctly? |
| Capacity / load | Steady-state at projected load | Will this hold during normal use? |
| Stress | Push past capacity until something breaks | Where does the bottleneck actually live? |
| Spike | Sudden 5×–10× burst, then back to baseline | Does autoscaling kick in fast enough? |
| Soak | Steady moderate load for hours/days | Memory leaks, slow degradation |
| Chaos | Add fault injection during load | What happens when a region fails under peak? |
All five are necessary at different points in the service lifecycle. Most teams do only "load" — and thus get surprised by leaks (caught only by soak), and outages (caught only by chaos).
7.2 Closed-loop vs open-loop¶
- Closed-loop generators: a fixed number of virtual users; each waits for a response before sending the next. Scales with backend latency.
- Open-loop generators: traffic at a fixed RPS, regardless of backend response time.
Open-loop is the realistic model. Real customers don't slow down because your backend is slow. Closed-loop masks capacity issues — it slows down with you, so the test never reveals queueing.
7.3 Tools¶
| Tool | Strength | Notes |
|---|---|---|
| k6 | Open-source, scriptable, modern | The default for new teams |
| Locust | Python, distributed | Good for complex scenarios |
| JMeter | Mature, GUI | Showing age; still common in enterprise |
| Gatling | Scala, Akka-based | Good performance; smaller community |
| wrk / wrk2 | Tiny, very fast | Open-loop by default; great for raw HTTP |
| Vegeta | Go-based, simple, open-loop | Excellent for raw HTTP load |
| Artillery | Node-based | Solid in JS shops |
| Locust + custom | Custom-instrumented for service | Used at scale |
wrk2 (or wrk's open-loop alternatives) is what you reach for when you need to verify the M/M/1 prediction holds. The default wrk is closed-loop and lies about latency at high load.
7.4 Load testing in production¶
Mature orgs run load against production. Reasoning: pre-prod doesn't have prod data, prod scale, prod dependencies. Load tests in pre-prod often miss real bottlenecks.
Production load testing requires: - Synthetic test traffic (tagged, doesn't pollute analytics). - Kill switch (stop in 1 second). - Limited scope (one region, one tenant). - Run during low-traffic windows initially.
It's high-leverage but high-risk. Net Reliability Engineering (Netflix's approach), Stress Tests (Google), GameDays — all variants.
8. Provisioning Patterns¶
8.1 Vertical scaling¶
Bigger instances. Easy mentally; limited by largest available SKU; usually expensive on $/req.
When: small services where horizontal scaling adds operational complexity not worth it.
8.2 Horizontal scaling¶
More instances. The default for stateless services.
When: stateless services. Coordination cost (load balancers, service mesh) is the trade-off.
8.3 Autoscaling¶
Automatic horizontal scaling based on metrics (CPU, queue depth, custom). Cloud-native (AWS ASG, GKE HPA, K8s HPA).
When: variable load. Trade-offs: - Reactive lag — autoscaling adds capacity after the metric crosses; tail latency suffers during the lag. - Cold starts — new instances need warm-up; routing fresh traffic to cold instances spikes latency. - Cost noise — bills become harder to predict.
The 2026 maturity bar: predictive autoscaling (scale before the metric crosses, based on forecast / schedule).
8.4 Cell architecture¶
Many smaller, isolated copies of the service ("cells"), each serving a subset of traffic. AWS, Google, Slack, GitHub all run cell architectures for highly-available services.
Properties: - Blast radius: a bug or outage affects one cell, not all. - Independent capacity per cell. - Independent scaling per cell. - Operational complexity: many cells = many things to manage.
When: high-SLO services (≥ 99.99%). Below that, the operational cost is hard to justify.
8.5 Provisioning lead time¶
Critical and often forgotten:
| Resource | Typical lead time |
|---|---|
| Cloud VMs (autoscale) | seconds |
| Cloud VMs (new SKU) | hours |
| Cloud reserved instances | days |
| Self-managed bare metal | weeks |
| New region / new datacenter | months |
| Custom hardware (GPU, TPU) | months to years |
Capacity plans must account for lead time. "We'll need 200 GPUs in 6 months" requires placing the order now if the lead time is 6 months. Reactive doesn't work for long-lead resources.
9. The Capacity Planning Artifact¶
A capacity plan is a document, refreshed quarterly. Live in the SRE / platform repo.
9.1 The template¶
# Capacity Plan — checkout-svc — Q3 2026
## Current state (as of 2026-07-01)
- RPS: 1,200 mean, 4,500 peak
- p99 latency: 380ms
- CPU headroom (peak): 38%
- Memory headroom (peak): 42%
- Connection pool headroom: 75%
- DB IOPS headroom: 60%
## Forecast (next 6 months)
- Traffic: +30% (driven by Q4 holiday)
- Feature: +5% per-request CPU (new pricing engine)
- Combined: +37% load
## Required capacity
- Peak load forecast: 4500 × 1.37 = 6,165 RPS
- Required CPU headroom at forecast peak: ≥ 30%
- Implication: scale from 50 pods to 75 pods (50% increase)
- Database: connection pool max from 200 to 300; verify DB IOPS ceiling
## Risks
- DB IOPS ceiling unclear; load test in August
- Pricing engine deploy in September; canary first
- Black Friday peak may exceed forecast; spare capacity in zone B
## Action items
- [ ] Pre-scale to 60 pods by Aug 1
- [ ] Pre-scale to 75 pods by Oct 15
- [ ] Run capacity load test by Aug 30
- [ ] Verify autoscaling can hit 100 pods within 2 minutes
- [ ] Negotiate DB connection pool with platform team
## Buffer
- Operating with 30% buffer above forecast through Q4
- Black Friday: provision 2× steady-state for the week
9.2 The plan review¶
Quarterly review. Attended by the service team, platform team, finance / FinOps, leadership.
- Validate forecast against actuals (last quarter's plan vs reality).
- Approve the next quarter's plan.
- Approve any pre-procurement / pre-provisioning.
This is one of the only places where reliability is negotiated with finance. Treat the meeting as such.
10. Multi-Region Capacity¶
Each region has its own capacity plan; the aggregate must absorb single-region failures.
10.1 N+1 vs N+2¶
For 99.99% SLO across 3 active regions, the 2 surviving regions must together absorb 100% of peak if any one fails. Each region is therefore sized for ½ of peak while normally serving ⅓ of it, i.e. it runs at ≤ ⅔ of its capacity (in general ≤ (N−1)/N), which matches the 1.5× multiplier in §10.2.
10.2 The geometric capacity cost¶
For active/active across N regions, total capacity = (N / (N-1)) × peak load.
| N | Capacity multiplier |
|---|---|
| 2 | 2.0× (one region must handle 100%) |
| 3 | 1.5× |
| 4 | 1.33× |
| 5 | 1.25× |
| 10 | 1.11× |
More regions = lower over-provisioning per region = lower cost-per-9. This is one of several reasons cell / multi-region architecture is the only path to high SLOs (revisited from doc 13 §11.2).
10.3 Active/passive¶
Cheaper but slower failover.
Failover takes minutes; SLO impact during failover is real. Used when the cost of N+1 active is too high. Common for legacy databases, expensive analytics.
10.4 Capacity per failure domain¶
Multi-region is one failure-domain dimension. Others: - AZ (within a region) - Cell (within an AZ) - Pod (within a cell) - Node (the underlying host)
For high-SLO services, plan capacity at every failure-domain level: can the system absorb the loss of one (zone, cell, node)? Express it as: "each cell is at 60% utilization; we can lose 2 of 5 cells."
11. Cost-Bounded Capacity¶
The honest equation: capacity costs money. Provisioning forever is unsustainable.
11.1 The trade-off¶
More headroom = more reliability and more cost. Less headroom = cheaper and riskier.
The cost-aware capacity plan answers: what's the minimum headroom that meets the SLO? That's the optimum operating point. Above it, you're spending for unused reliability; below it, you're risking budget burn.
11.2 The cost projection¶
Every capacity plan has a cost line:
Current quarterly cost: $120k
Forecast quarter: $156k (+30%)
With 30% headroom: $203k
Net: $83k additional spend per quarter to maintain headroom.
This number goes to finance. They either approve, push back, or invest in efficiency work (lower per-request cost). Capacity planning is, at this point, financial planning.
11.3 Spot / pre-emptible capacity¶
Mature orgs use cheaper, pre-emptible capacity (AWS Spot, GCP Preemptible, Azure Spot) for non-critical workloads. Capacity plans separate "must be on-demand" from "can be spot."
A pattern: 80% on-demand for the steady state, 20% spot for burst. Spot's preemption is acceptable because the steady state covers SLOs.
11.4 Right-sizing¶
Most services run on instances 2-3× larger than they need. Quarterly right-sizing: - Per service, look at last quarter's peak resource use. - If peak < 50% of instance, downsize to next SKU. - Run a load test to verify.
This is one of the highest-ROI activities for any platform team — typical savings of 15-30% of compute cost.
12. Capacity SLIs and Platform SLOs¶
Capacity itself has SLIs. The platform team owns these.
12.1 Capacity-quality SLIs¶
| SLI | Definition | Target |
|---|---|---|
| Headroom compliance | % of (service × resource) cells with ≥ 30% headroom | ≥ 95% |
| Forecast accuracy | abs(actual - forecast) / actual | ≤ 20% |
| Provisioning lead time | Time from "we need more" to "available and validated" | ≤ 1 week for cloud, ≤ 1 month for self-managed |
| Capacity-related incidents | Incidents whose contributing factor is capacity | ≤ 1 per quarter |
These are the platform team's measure of capacity-planning health. If forecast accuracy is consistently > 20%, the model is wrong; revisit. If capacity-related incidents are rising, headroom is too tight or forecasts too optimistic.
12.2 The "capacity dashboard"¶
A single, cross-service dashboard showing: - Headroom heatmap per service × resource. - Forecast curves for the next 6 months. - Recent capacity-related incidents. - Procurement / provisioning in flight.
This dashboard is for leadership. It's the macro view of organizational reliability investment. Ship it; review it monthly.
13. The Chicken-and-Egg of New Services¶
How do you capacity-plan a service that doesn't exist yet?
13.1 The bootstrapping options¶
- Analogous services. "This is like our existing browse service in shape." Use that as the baseline; adjust.
- Synthetic load. Build the service; load test against projected load before launch.
- Conservative initial provision. Provision 5× expected; let the early operational data inform the right size.
- Soft launch / canary. Release to 1% of traffic; measure; extrapolate.
In practice: a combination. Analogous estimate → conservative initial provision → soft launch + canary → adjust within first month. The PRR (doc 17) bakes capacity planning into the launch checklist.
13.2 The "unknown traffic shape" trap¶
A new service often has an unknown traffic shape — bursty? steady? 10× peak-to-mean? Don't pre-commit to autoscaling thresholds; instrument heavily, watch the first month, then tune.
14. Worked Example: A 12-Month Checkout Forecast¶
Concrete, end-to-end.
14.1 Inputs¶
- Q1 traffic: 800 RPS mean, 2400 peak
- Year-over-year growth: +25%
- Q4 holiday seasonality: +60% over Q3 baseline
- New feature in Q3: +10% per-request CPU
- New feature in Q4: +5% per-request memory
14.2 Forecast model¶
Q1 baseline: 800 RPS mean, 2400 peak
Q2: 800 × 1.05 (org growth) = 840 mean, 2520 peak
Q3: 840 × 1.05 × 1.10 (CPU feature) = 970 effective load
Q4: 970 × 1.05 × 1.05 × 1.60 (holiday) = 1,710 effective load
Peak: Q4 peak ≈ 1710 × 3 = 5,130 effective RPS-equivalent CPU
14.3 Capacity plan¶
Q2 needs: scale from 30 pods → 32 pods (small adjustment)
Q3 needs: scale to 40 pods (CPU feature accounted)
Q4 needs: scale to 65 pods, possibly additional region
Procurement:
- More AWS reserved instances by Aug 31 for Q4 capacity
- Validate auto-scale to 80 pods in Q4 (load test in October)
- Negotiate DB connection pool: 200 → 350
Cost:
- Q1: $80k/quarter
- Q4: $156k/quarter (+95%)
14.4 Validation¶
October load test: actual peak handled at 60 pods with 25% headroom. Plan was conservative; release 5 pods of pre-provisioning for Q4 to keep cost in check. Adjust forecast model: holiday seasonality was +50%, not +60%. Re-calibrate next year.
This is what mature capacity planning looks like — quantitative, iterative, calibrated.
15. Pitfalls¶
- Looking at utilization, not headroom. Latency surprises before utilization tells you anything.
- Forecasting linearly when growth is compound. Massively under-estimates.
- One bottleneck only. Forgetting connection pools, FDs, kernel structures.
- No load test. Provisioning capacity that doesn't deliver.
- Closed-loop load tests. Mask queueing.
- Reactive only. Lead times bite when the world surprises.
- No multi-region capacity. Single-region failure means full outage.
- No quarterly review. Plan drifts; team learns nothing.
- No cost line. Finance pushes back during budget cycle; everyone surprised.
- Right-sizing skipped. 30%+ of compute spend wasted on oversized instances.
- No forecast validation. Models perpetually wrong; nobody recalibrates.
- Capacity SLIs not measured. Platform team can't show value.
- No game day for capacity loss. Failover untested; surprises during real outage.
- No procurement plan for long-lead resources. GPU / hardware requests delayed by months.
- All resources sized to peak. Pays for capacity that's idle 95% of the year.
16. Mental Models¶
Headroom, not utilization. The forward-looking metric.
30/50/70. Below 30% = emergency; 30–50% = act this quarter; 50–70% = plan ahead.
The bottleneck migrates. Plan for which one is next, not which one is current.
Forecasts are wrong; the point is bounded wrong. Express ranges, not points; recalibrate monthly.
Open-loop load testing reveals queueing; closed-loop hides it.
Lead time is part of the plan. Long-lead resources need orders months in advance.
Capacity is finance. The cost line is non-negotiable; the headroom-vs-cost trade-off is explicit.
Multi-region is the only path to high SLOs. Geometric capacity costs make it cheaper as N grows.
The capacity dashboard is for leadership. Ship it; review monthly.
Right-size quarterly. It's the highest-ROI cost-saving activity.